SPECIAL PROTECTION SCHEMES IN OPERATION AT ITAIPU POWER PLANT RUI JOVITA G. C. DA SILVA * JOSÉ BENEDITO MOTA JÚNIOR ROBSON ALMIR DE OLIVEIRA JOSÉ GREGÓRIO ACHA NAVARRO MARCELINO PEREIRA DE ALMEIDA EVONYR BORDIN FILHO FERNANDO VEGA DAHER ALEXANDRE GONÇALVES LEITE CIGRE 2006 - B5-203 1 TRANSMISSION SYSTEM 6.300 MW 23 % 7.000 MW 94 % 1.300 MW 6% 6.300 MW 90 % CIGRE 2006 - B5-203 2 INSTALLED CAPACITY EVOLUTION: GENERATION X TRANSMISSION. 50 Hz Sector CIGRE 2006 - B5-203 3 INSTALLED CAPACITY EVOLUTION: GENERATION X TRANSMISSION. 60 Hz Sector CIGRE 2006 - B5-203 4 DESCRIPTION OF THE SPECIAL PROTECTION SCHEMES 60 HZ - 17 ACTIONS stability 7 self-excitation 1 overvoltage 1 overfrequency 3 overload 3 voltage collapse 1 damping 1 50 HZ - 14 ACTIONS overfrequency 5 frequency collapse 3 overvoltage 4 overload 2 CIGRE 2006 - B5-203 5 CS U10 TRIP U10 Frequency Rate Scheme CS U11 TRIP U11 CS U12 TRIP U12 CS U13 TRIP U13 CS U14 TRIP U14 CS U15 81D1 Taxa 1 f t 1,2 Hz TRIP U15 CS T1 CS U16 TRIP U16 s CS U17 Taxa 3 f t TRIP U17 2,4 Hz CS U18 s OR 81D2 Taxa 2 f t 1,4 Hz TRIP U18 Send signal to open 765 kV lines in Foz do Iguaçu CS T2 s Taxa 3 f t 2,4 Hz s CIGRE 2006 - B5-203 6 SCHEME TO AVOID FREQUENCY COLLAPSE U01 And U02 And And And Off Separate U01 Separate U02 And signal from ST-FI of the blocking of 4 or more converters And disconect one unit of U01, U02, U03 ou U04 And Relé 81 f t CIGRE 2006 - B5-203 7 OVERLOAD ON LINES Overload LT IPU-MD 1 t = 5s And Open circuit breaker 84LI2 And + t = 3s 43MD1 Overload LT IPU-MD 2 And t = 5s And + t = 3s 43MD2 CIGRE 2006 - B5-203 Open circuit breaker 44L22 Open circuit breaker 84LI1 Open circuit breaker 44L11 8 PERFORMANCE 60 Hz Time to re-synchronize was reduced about 5 min. Its 1 min 30 s now. 50 Hz switches manually controlled => self-excitation => operators are more familiarized CIGRE 2006 - B5-203 9 PERFORMANCE 60 Hz 159 PLCs actuations 13 errors - associated with maintenance, PLCs design and auxiliary equipments failures. Logic 02 Logic 04 Logic 05 Logic 06 Logic 08 Logic 09 Logic 11 Logic 12 Logic 13 Logic 14 Logic 15 Total Number of Actuation of the PLCs Logics 76 2 25 3 15 13 4 8 5 3 5 CIGRE 2006 - B5-203 10 PERFORMANCE 60 Hz Logic Logic 2 Misoperation Causes Tripping of generators due to failure in auxiliary equipment, which provide to PLC the status of transmission line. Tripping of generators due to short circuit in DC source of the Ivaiporã PLC, without transmission lines opening. This wrong actuation caused load interruption in Brazilian power system. Refusal of operation due to design error. Tripping of generators due to: communication and auxiliary equipment (which provide the status of series capacitor to PLC) failures. Tripping of one, instead of two, generating unit due to wrong period of load set in PLC. There weren’t stability problems to the power system. CIGRE 2006 - B5-203 11 PERFORMANCE 60 Hz Logic Logic 8 Logic 9 Logic 6 Logic 13 Misoperation Causes Tripping of generators due to failure in auxiliary equipment, which provide to PLC the status of transmission line. Communication problem caused generating units tripping without event in the system. No tripping of generating units due to failure in auxiliary equipment, which provide the power flow on transformers to PLC. Tripping of generators due to PLC software error, without overload in transformers. Three actuations with disconnection of generating units during overload relay maintenance at Ivaiporã substation. Tripping of generators due to PLC software error. CIGRE 2006 - B5-203 12 PERFORMANCE 60 Hz SCHEMES INDEPENDENT FROM PLCs: * scheme against self-excitation - one correct actuation during 2002 major blackout. * scheme to increase damping with Brazil Southern region - one correct actuation during an opening of 765 kV S-SE interconnection. * scheme to control overfrequency in Brazil Southern region - one incorrect actuation in 1994 during relay maintenance, tripping all 765 kV lines in Foz do Iguaçu substation. CIGRE 2006 - B5-203 13 PERFORMANCE 50 Hz scheme to avoid the separation of the interconnected system Itaipu-Ande – two correct actuation, with generating unit tripping by frequency rate to control overfrequency. CIGRE 2006 - B5-203 14 PERFORMANCE 50 Hz One was during the 1999 major blackout, and the interconnection Itaipu-Ande was opened by the actuation of the 220 kV overvoltage relay (overvoltage above 286 kV for more than 1s), causing blackout in Ande power system. Because of this occurrence the scheme to avoid frequency collapse in the Ande power system was created. The other actuation avoids blackout in Ande power system during HVDC bipole blocking. CIGRE 2006 - B5-203 15 PERFORMANCE 50 Hz About SPSs incorrect actuation, there were only one, which occurred in 1995 during maintenance, when there was an accidental operation of the 500 kV line protection, signalizing a two-phase fault. This resulted in interconnection Itaipu-Ande opening and blackout in Ande power system. CIGRE 2006 - B5-203 16 CONCLUSIONS Despite the number of Special Protection Schemes installed at Itaipu power plant, they can be characterized by their simplicity and good performance. They were installed since the beginning of plant operation and have been provided security to the electrical system and equipments. CIGRE 2006 - B5-203 17 CONCLUSIONS Most of SPSs are designed to act during complex problems in the interconnected system, the exception are the SPSs implemented by PLCs in 60 Hz system, which act during simple contingencies too. The SPSs actuations avoided interruption of load, or even major blackout, throughout Brazilian and Paraguayan power system, mainly those designed to maintain system stability and to avoid voltage and/or frequency collapse. CIGRE 2006 - B5-203 18 CONCLUSIONS It´s important to highlight the familiarization of Itaipu operators with all these schemes and their actuations, characterized mainly by the right auxiliary switches positioning, on 50 Hz sectors, and by the short period to re-synchronize generating units disconnected by SPSs, in 60 Hz sector. CIGRE 2006 - B5-203 19 CONCLUSIONS The SPSs have been presented very good performance. The misoperations are associated with equipment maintenance and with failures of PLCs design or auxiliary equipments. The SPSs implemented by PLCs present less than 10 % of incorrect actuations and/or refusals. The others SPSs have so few actuations to allow a statistics calculation, but the incorrect actuations didn’t repeat for years. CIGRE 2006 - B5-203 20 SPECIAL REPORT Question 2.3 How important are communication issues (availability, reliability, etc.) for the implementation of SPS ? Deve-se procurar alcançar uma disponibilidade o mais próxima possível de 100 % para os recursos de comunicação utilizados em SPS. Qualquer redução implica em indisponibilidade do SPS. O mesmo vale para uma recepção correta do sinal enviado. Para garantir isso pode-se enviar os sinais por meios diferentes. CIGRE 2006 - B5-203 21 SPECIAL REPORT Question 2.3 Have any risk been identified involving overfunction in case of duplication/triplication of equipments ? É uma possibilidade. O projeto do SPS deve sempre prever que a sua possibilidade de falha deve ser mínima face a solicitação mais crítica. Assim, uma duplicação/triplicação tem o objetivo de evitar atuações desnecessárias, mas não podem aumentar a possibilidade de falha na pior condição. CIGRE 2006 - B5-203 22 SPECIAL REPORT Question 2.3 Have any misoperation been experienced that have had an influence on decision concerning systems’ maintenance ? Sim. Muitas. As rotinas e procedimentos de manutenção dos SPSs requerem determinadas condições do sistema que muitas vezes podemimplicar em restrições eltro-energéticas. CIGRE 2006 - B5-203 23