RNP Measurement Experiments
End to End Performance WG
GT-Medições2
Prof. José Augusto Suruagy Monteiro (coordinator)
Universidade Salvador
http://wiki.gt-med.ufsc.br/wiki
[email protected]
May 29th, 2006
© 2006 – RNP/E2E Performance WG
Measurement Activities at RNP
Context
•
QoS WG (2002-2003):
– Netflow based flow measurement infrastructure
•
QoS2 WG (2003-2004):
–
–
–
–
•
Netflow Data Analysis (Traffic Matrix)
Passive Measurements (NetraMet)
Active Measurements with AMP
Active Measurements with OWAMP
Measurement WG (2004-2005):
– piPEs-BR Development and Deployment
– RNP Observatory
– SLA Monitoring Environment
•
Measurement 2 WG (2005-2006):
– piPEs-BR/GFD Development and Deployment
– Interoperation with other network domains (perfSONAR integration)
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
Current Activities (E2E Performance WG)
piPEs-BR/GFD
• GFD = General Framework Design – Géant2/JRA1 Deliverable
• piPEs-BR/GFD is an architecture designed to provide
measurement information using Web Services in order to
interoperate with other network domains (eg. Internet2 and
Geant2).
• Some components have been designed and are being developed
to provided the Services specified in the GFD document (MP, MA,
LS, TopS, TS, RP).
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
Current Activities (E2E Performance WG)
piPEs-BR/GFD
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
piPEs-BR/GFD
Modules Interaction Example
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
piPEs-BR/GFD
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
perfSONARUI Access to RNP´s Utilization RRD MA
perfSONARUI and RNP´s Utilization RRD MA
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
Current Status
MP Deployment
Active
Temporarily
out of
service
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
Current Status
New MPs in Rio and São Paulo with CDMA kits
Courtesy photos of PoP-SP (Fábio de Castro)
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
Current Status
MPs at UFSC and UNIFACS with GPS kits
Courtesy photo of PoP-SC/UFSC (Guilherme Rhoden)
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
piPEs-BR/GFD
Command Line MP (CL MP)
•
•
Joint work with Internet2 (Jeff)
Implement CL MP modules based on perfSONAR messages
– Mesurement Executor
– Request Manager
– Configuration Module
•
•
•
Test on RNP backbone CL MP using OWAMP
Design OWAMP messages standard based on existing messages
Deploy CL MP service on main RNP connections
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
CL MP Graphics: Ping
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
CL MP Graphics: OWAMP
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
piPEs-BR/GFD: Current Status
Publish and Discovery Service (LS)
•
•
•
•
•
Uses UDDI technology
Development of a Lookup library
for the DPS
Adaptation of the DPS to work
with NMWG schema
Developed in JAVA
Interest in Multi-LS design and
testing
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
piPEs-BR/GFD
Test Manager (TM)
•
•
Will implement TopS and TS services
The idea with this component is to facilitate the visualization tool
development incorporating some functionalities such as:
– Data recovering
– Test scheduling
– Data composition
•
Topology Service – TopS
– It will store and provide topology information to users.
– It can have a software to “discover” the network topology and a specialized
database to store the topology information
•
Transformation Service – TS
– Aggregate, correlate or filter the data according to users needs.
– Also catch and store the measurement data to users avoiding new
connections and message sharing between users and other services.
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
piPEs-BR/GFD
Resource Protector (RP)
•
•
•
•
•
The first version will control the RNP´s MPs schedules in order to protect
network resources.
The initial resource to be protected will be link bandwidths.
The information about the MP schedules and required bandwidth will be
stored in a relational database.
The total consumed bandwidth per link for the desired time frame will be
compared with link capacities and the test will be authorized or not
depending on established policies (eg. Upper limit on link capacity
utilization and user data utilization).
Initially, only the services for MP tests control will be implemented.
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
piPEs-BR/GFD: Current Status
ICE
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
ICE: Visualization Tool
Tool Demonstration
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
ICE: Visualization Tool
Tool Demonstration
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
ICE: Visualization Tool
Tool Demonstration
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
perfSONAR Collaboration
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
End to End Performance WG
Working Group Members
UFSC Team:
• Edison T. L. Melo ([email protected])
• Fausto Vetter ([email protected])
• Guilherme E. Rhoden ([email protected])
UNIFACS Team:
• Herbert M. Souza ([email protected])
• Ivan Koga ([email protected])
• Ivo Koga ([email protected])
• Leobino Sampaio ([email protected])
• Rafael Costa ([email protected])
GT-Medições2 7th WRNP – Curitiba – May 29th, 2006
Download